Perfsys — AWS Consulting Partner

Heroku to AWS Migration: How We Moved a Live Fitness App Backend in 7 Weeks

7

weeks to production on AWS

11

blockers found in Phase 1

0

user-facing incidents

Key Insights

Location

Germany

Project duration

7 weeks to production, then ongoing support

Industry

Fitness equipment and apps

Technologies used

Amazon ECS Fargate, MongoDB Atlas, Amazon S3, AWS Lambda, Amazon CloudFront, Terraform, GitHub Actions

Introduction

A fitness app cannot stop working because its backend is moving. This client, a German fitness equipment brand with a live strength-training app, had its backend on an outgoing agency's Heroku setup and wanted it in an AWS account it owns.

This Heroku to AWS migration case study covers Phase 2: Active Migration and Phase 3: Post-Migration Support. Production switched to Amazon ECS Fargate in Frankfurt 7 weeks after the first build, with no user-facing incident and no data loss. Phase 1, Discovery and Planning, is covered in our AWS consulting case study.

Results at a Glance

  • 7 weeks from the first build to production on AWS
  • 0 user-facing incidents and no data loss at the switch
  • 796 records with media links moved to the new storage, with 0 conflicts and none left behind
  • Every app version kept working, including builds that no DNS change could reach
  • 6 production releases through the new pipeline in the first 3 weeks
  • 2 recurring costs removed: the agency's backup server and the separate email plan

Why Did the Client Migrate From Heroku to AWS?

The client is a German fitness equipment brand with an iOS and Android strength-training app and a few thousand users. A small in-house team owns the product, and an external agency had built and hosted the backend.

Phase 1 recorded 11 migration blockers, 4 of them rated high-severity, and left us with a verified inventory, a chosen plan (keep MongoDB Atlas, replace what the agency controlled) and a 6-phase cutover plan. The migration started from that plan.

Phase 2: Active Migration

How Do You Test a Heroku to AWS Migration Before Production?

Staging and production are built from one Terraform module, so what passed in staging behaved the same live. Staging passed a 15-point acceptance check before production work began.

AWS migration timeline: 7 weeks from first build to production
Heroku to AWS migration timeline: discovery, build start on 19 August, staging accepted 29 September, live on AWS 8 October, legacy host retired around January 2027
About 3 weeks of consulting, then 7 weeks from the first build to production on AWS.

How Is the New AWS Backend Built?

Heroku to AWS migration: simplified architecture diagram
Heroku to AWS migration: simplified architecture diagram of the new AWS backend, with the mobile and web clients, the ECS Fargate API, the media pipeline, MongoDB Atlas, Amazon SES, and the delivery and observability tools
Simplified architecture of the new backend: the main services and connections in the client's own AWS account in Frankfurt.

Containers on Amazon ECS Fargate. The Node.js API runs behind an Application Load Balancer, in private subnets in Frankfurt. It is stateless and health-checked, so scaling out is a setting change.

A database that stayed, with a private path. The MongoDB Atlas cluster sits in the client's own Atlas account and connects to AWS over VPC peering. A daily snapshot export copies the database to S3 as a second backup.

A media pipeline in place of the agency service. Uploads land in Amazon S3. An SQS queue feeds a Lambda worker for images and AWS Elemental MediaConvert for video, and CloudFront serves the results. Failed jobs go to a dead-letter queue that raises an alarm.

Heroku to AWS migration: media pipeline
Heroku to AWS migration media pipeline: an app upload lands in Amazon S3, an SQS queue feeds a Lambda worker for images and MediaConvert for video, CloudFront serves the results, and failed jobs go to a dead-letter queue that raises an alarm
The media pipeline that replaced the agency's media service, with an alarm for every failed job.

Email, jobs and secrets. Amazon SES sends sign-in codes from the brand's own domain. EventBridge Scheduler runs the maintenance jobs, with alarms for failed and missed runs, so the GDPR deletion job can no longer stop silently. Secrets live in AWS Secrets Manager.

Releases and monitoring. GitHub Actions deploys with keyless sign-in to AWS. A merge goes to staging, and a release tag promotes the same tested image to production. CloudWatch alarms and OpenTelemetry traces, with personal data redacted, alert the team by email and Slack. We built similar visibility for another client: see the serverless observability case study.

Heroku to AWS migration: release flow
Heroku to AWS migration release flow: a merge goes to staging, a release tag promotes the same tested image to production, and CloudWatch and OpenTelemetry alert the team by email and Slack
From merge to production: the same tested image moves through the pipeline, with monitoring on the other side.

How Do You Keep Old App Versions Working During the Cutover?

Old app versions on users' phones still called the old host. We turned that old address into a thin forwarder to the new API on AWS. New app builds and the admin panel call the new domain directly. The forwarder is retired once the old versions drop out of use.

Mobile app backend cutover with a legacy forwarder
Heroku to AWS migration cutover: old app builds reach the new API through a thin forwarder on the legacy address, while new builds and the admin call it directly
Every app version reached the new backend from the first minute, with no forced update on switch day.

Before the switch, we rehearsed the forwarder on staging and simulated old app versions against it. On switch day, traffic moved to AWS in one step. The database did not move, so there was nothing to sync. Users stayed signed in, and 796 stored media links were moved to the new CDN with 0 conflicts.

"The database stayed where it was and the old address became a forwarder, so there was nothing to sync and nothing for users to notice. That is what a migration built on a verified inventory gives you."

— Eugene Orlovsky, Founder and CEO, Perfsys

Phase 3: Post-Migration Support

The client continued with Perfsys through AWS Marketplace on a 6-month CloudCare Standard plan covering foundation, cutover, stabilization, operations, hardening and a Well-Architected review with handover.

Here is where the platform stands now:

  • Live on AWS since day 50 of the build, with 6 production releases through the pipeline in the first 3 weeks
  • 95% of requests answered in 0.5–0.6 seconds, at about 1% CPU and 20% memory, which leaves room for the app relaunch
  • No incidents in the first two weeks of production, checked daily and then weekly

We now run day-to-day operations and support the client's v2.0 app relaunch, planned for December. The roadmap covers:

  • Retiring the legacy host and old media storage once old app versions drain, expected around January 2027
  • Backup and disaster-recovery testing
  • Cost and security hardening
  • An AWS Well-Architected review and handover

What Did the Client Gain From Moving Off Heroku?

  • Full ownership. The client owns every account and all of the infrastructure code, and releases run from its own pipeline.
  • 2 recurring costs removed. The agency's backup server and the separate email plan are gone.
  • A backend the team can change. Releases are automated and environments are reproducible, with monitoring in place.
Moving off an agency or a platform you don't control?
Moving off an agency or a platform you don't control?

We plan and run AWS migrations for startups and SMBs, from discovery to a cutover your users don't notice.

Book a Discovery Call
Explore AWS Migration

FAQ

In this project, about 3 weeks of discovery, then 7 weeks from the first build to production on AWS. Retiring the old host follows later, once old app versions drop out of use.

Keep the old address alive as a thin forwarder to the new backend. Ship new app builds that call a domain you control, and retire the forwarder once the old versions drain.

In this project, yes. Traffic moved to AWS in one step with no user-facing incident and no data loss. The database did not move, so there was nothing to sync, and users stayed signed in. The old address kept working as a forwarder for older app versions.

Yes, through CloudCare managed support packages for ongoing monitoring and incident response.

Mykyta Glushko
Mykyta Glushko

Software Engineer at Perfsys with hands-on experience building scalable backend systems on AWS using Python and TypeScript. He works directly on cloud infrastructure projects, bringing practical engineering depth to every topic he covers.

Recommended for You

View All News

AWS Experts, On-Demand

Need to move fast? Our cloud team is ready to scale, secure, and optimize your systems. Get serverless expertise, 24/7 support, and seamless CI/CD pipelines when you need it most.

Please accept cookies to load the booking widget.